LESCO New Connection – Application, Fee and Status

Don’t know how to Apply for LESCO New Connection? Don’t worry here is the detailed guide for applying LESCO New Mete Connection and how to track application. As we know that LESCO provides electricity to millions in Lahore and nearby regions. For new customers seeking a connection, understanding the application process, necessary documentation, fees, and timelines is essential. So let us guide you in this regard and make LESCO New Electricity Connection easy for you.

Categories of LESCO New Connections

LESCO categorizes new connections by load requirement, which affects the fees, required documents, and processing times:

  • Category One: Up to 15 kW (mainly residential)
  • Category Two: 16 kW – 70 kW (small commercial)
  • Category Three: 71 kW – 500 kW (large commercial and industrial)

Each category has unique requirements and associated costs, discussed in detail below.

How to Apply for a LESCO New Connection?

Online Application Process

LESCO offers an online application process, making it easy to submit and track requests. Here’s a step-by-step guide:

  1. Visit LESCO’s ENC Portal: Navigate to the Electricity New Connection (ENC) section on the LESCO website.
  2. Create an Account: Register by providing basic information if you’re a new user.
  3. Complete the Application Form: Fill out details accurately, specifying your connection requirements.
  4. Upload Required Documents: Attach clear, scanned copies of documents, keeping each file under 300 KB.
  5. Submit the Application: After reviewing, submit the application. You’ll receive a tracking ID to monitor your status.
  6. Print Confirmation: Keep a printed copy of your application for future reference.
LESCO New Connection Application

Manual Application Process

For those without internet access or preferring a physical submission, the manual process is straightforward:

  1. Obtain an Application Form: Download it from LESCO’s website or collect it from a LESCO office.
  2. Fill Out the Form: Complete the form accurately and attach the required documents.
  3. Submit at a LESCO Office: Hand in the form and documents at your local LESCO office.
  4. Receive Confirmation: LESCO will verify your documents and provide a demand notice outlining the next steps.

Required Documents

LESCO requires specific documents to process your application:

  • Proof of Property Ownership: A property registry or allotment letter confirming ownership.
  • Attested CNIC Copies: Provide copies of both the applicant’s and a witness’s Computerized National Identity Cards.
  • Neighbor’s LESCO Bill Copy: Helps verify the property’s location.
  • Wiring Contractor’s Test Report: A safety compliance certificate from a licensed contractor.
  • Applicant’s Undertaking: A signed statement confirming compliance with LESCO’s regulations.

Processing Times for New Connections

Processing times vary by connection category:

Connection CategoryEstimated Processing Time
Up to 15 kW8-10 days
16 kW to 70 kWUp to 44 days
71 kW to 500 kWUp to 73 days

These timelines can be influenced by factors such as site inspections and document verification.

Fees for LESCO New Connections

Connection fees are based on the type of setup:

  • Single-phase Connection Fee: Approx. PKR 93,000
  • Three-phase Connection Fee: Approx. PKR 235,000

Check the LESCO website for the latest fee structure, as these rates may change due to regulatory updates.

Key Steps After Application Submission

Site Inspection

After submitting your application, LESCO will schedule a site inspection to confirm that all electrical installations meet safety standards. Prepare by ensuring accessibility and completed wiring according to LESCO’s norms.

Communicating with LESCO

Maintaining clear communication with LESCO is essential. Use your tracking ID to monitor the application’s progress. If additional documentation is required, respond promptly to prevent delays.

Final Connection Activation

Once approved and fees are paid, LESCO will set a date to connect electricity to your property. Ensure your availability on this date for any last checks or installations.

FAQs

You can check the status of your application by visiting the ENC website and entering your tracking ID or contacting the relevant LESCO office directly.

A demand notice is an official document issued by LESCO that outlines the fees associated with your new connection request. It acts as a challan form that you must pay at designated banks to proceed with your application.

Yes, even if you apply online, you must print out your submitted application form and submit it along with all required documents at your nearest LESCO office.

Yes, tenants can apply for a new LESCO connection, but they must provide a No Objection Certificate (NOC) from the landlord along with the standard documentation. This NOC confirms that the landlord permits the tenant to take the electricity connection.

If your application is rejected, LESCO will provide reasons for the rejection. You can address these issues and reapply or appeal the decision by submitting a formal request at your local LESCO office, along with any additional required documentation.

LESCO may have specific programs or subsidies aimed at assisting low-income households with their electricity connections. It is advisable to inquire directly with LESCO about any available assistance or reduced rates for eligible applicants.

To request a change in your connection load, you need to submit an application to LESCO, specifying the desired load adjustment. Depending on the increase or decrease in load, additional charges or refunds may apply. Ensure you provide all necessary documentation to support your request.

Failure to pay the demand notice within the specified timeframe can result in penalties, including additional charges on your bill or cancellation of your application. It is essential to adhere to the payment deadlines provided in your demand notice to avoid complications.

Conclusion

Obtaining a LESCO new connection is a straightforward process when equipped with the right information. By understanding the connection categories, necessary documentation, application methods, and associated fees, you’ll navigate the process confidently. Whether you choose to apply online or manually, proper preparation and clear communication with LESCO can make this process hassle-free, allowing you to enjoy uninterrupted electricity soon.