Don’t know how to Apply for LESCO New Connection? Don’t worry here is the detailed guide for applying LESCO New Mete Connection and how to track application. As we know that LESCO provides electricity to millions in Lahore and nearby regions. For new customers seeking a connection, understanding the application process, necessary documentation, fees, and timelines is essential. So let us guide you in this regard and make LESCO New Electricity Connection easy for you.
Categories of LESCO New Connections
LESCO categorizes new connections by load requirement, which affects the fees, required documents, and processing times:
- Category One: Up to 15 kW (mainly residential)
- Category Two: 16 kW – 70 kW (small commercial)
- Category Three: 71 kW – 500 kW (large commercial and industrial)
Each category has unique requirements and associated costs, discussed in detail below.
How to Apply for a LESCO New Connection?
Online Application Process
LESCO offers an online application process, making it easy to submit and track requests. Here’s a step-by-step guide:
- Visit LESCO’s ENC Portal: Navigate to the Electricity New Connection (ENC) section on the LESCO website.
- Create an Account: Register by providing basic information if you’re a new user.
- Complete the Application Form: Fill out details accurately, specifying your connection requirements.
- Upload Required Documents: Attach clear, scanned copies of documents, keeping each file under 300 KB.
- Submit the Application: After reviewing, submit the application. You’ll receive a tracking ID to monitor your status.
- Print Confirmation: Keep a printed copy of your application for future reference.

Manual Application Process
For those without internet access or preferring a physical submission, the manual process is straightforward:
- Obtain an Application Form: Download it from LESCO’s website or collect it from a LESCO office.
- Fill Out the Form: Complete the form accurately and attach the required documents.
- Submit at a LESCO Office: Hand in the form and documents at your local LESCO office.
- Receive Confirmation: LESCO will verify your documents and provide a demand notice outlining the next steps.
Required Documents
LESCO requires specific documents to process your application:
- Proof of Property Ownership: A property registry or allotment letter confirming ownership.
- Attested CNIC Copies: Provide copies of both the applicant’s and a witness’s Computerized National Identity Cards.
- Neighbor’s LESCO Bill Copy: Helps verify the property’s location.
- Wiring Contractor’s Test Report: A safety compliance certificate from a licensed contractor.
- Applicant’s Undertaking: A signed statement confirming compliance with LESCO’s regulations.
Processing Times for New Connections
Processing times vary by connection category:
| Connection Category | Estimated Processing Time |
|---|---|
| Up to 15 kW | 8-10 days |
| 16 kW to 70 kW | Up to 44 days |
| 71 kW to 500 kW | Up to 73 days |
These timelines can be influenced by factors such as site inspections and document verification.
Fees for LESCO New Connections
Connection fees are based on the type of setup:
- Single-phase Connection Fee: Approx. PKR 93,000
- Three-phase Connection Fee: Approx. PKR 235,000
Check the LESCO website for the latest fee structure, as these rates may change due to regulatory updates.
Key Steps After Application Submission
Site Inspection
After submitting your application, LESCO will schedule a site inspection to confirm that all electrical installations meet safety standards. Prepare by ensuring accessibility and completed wiring according to LESCO’s norms.
Communicating with LESCO
Maintaining clear communication with LESCO is essential. Use your tracking ID to monitor the application’s progress. If additional documentation is required, respond promptly to prevent delays.
Final Connection Activation
Once approved and fees are paid, LESCO will set a date to connect electricity to your property. Ensure your availability on this date for any last checks or installations.
FAQs
Conclusion
Obtaining a LESCO new connection is a straightforward process when equipped with the right information. By understanding the connection categories, necessary documentation, application methods, and associated fees, you’ll navigate the process confidently. Whether you choose to apply online or manually, proper preparation and clear communication with LESCO can make this process hassle-free, allowing you to enjoy uninterrupted electricity soon.